February 2020
Features

Innovative strategy increases profitability of ultra-deepwater fields

To solve complex issues related to developing deepwater reserves in the GOM, a common-sense approach utilizing appropriate technology enables operators to profitably capture critical dynamic reservoir data and increase ultimate recovery.
Roy Shilling / Frontier Deepwater Appraisal Solutions LLC Chuck White / Frontier Deepwater Appraisal Solutions LLC Vamsee Achanta / Frontier Deepwater Appraisal Solutions LLC Paul Hyatt / Frontier Deepwater Appraisal Solutions LLC Howard Day / Frontier Deepwater Appraisal Solutions LLC

For nearly two decades, operators working in the Gulf of Mexico have had little success developing the massive reserves of Lower Tertiary projects in ultra-deep waters. They have failed, primarily, because their attempts to adapt subsea systems for exploitation of these complex resources have been thwarted by technological challenges, lengthy appraisal processes, and high-cost Phase 1 subsea development schemes with unacceptable levels of risk.

Fig. 1. The Lower Tertiary is characterized by very high drilling and completion costs. Wells can reach 40,000 ft, and require >250 days to drill.
Fig. 1. The Lower Tertiary is characterized by very high drilling and completion costs. Wells can reach 40,000 ft, and require >250 days to drill.

Lower Tertiary wells are the deepest, most complex and highest-pressure wells in the GOM, Fig. 1. High-pressure Paleogene reservoirs are in extreme water depths (4,000 to 10,000 ft) and exhibit mudline pressures that can approach and exceed 15,000 psi. Wells drilled into these formations may reach total measured depths of up to 40,000 ft. Significant reservoir uncertainties, which stem from a lack of production history and overhanging salt canopies, make seismic imaging extremely challenging and provide further barriers to project sanction.

Historically, operators have drilled numerous, costly appraisal wells to gather static information from electric logs and cores. But this static information still does not provide the industry with the critical insights needed to de-risk a project and determine commerciality. These factors require production and completion performance information to adequately define:

  • Faulting and connectivity
  • Depletion drive mechanism
  • Sand control needs
  • Intervention requirements
  • Reserve recovery per well.

Without dynamic reservoir information, these questions remain unanswered, making it difficult for operators to justify expensive high-risk investments to exploit this deepwater resource. As a result, despite estimates of 40 Bboe reserves in place, the Lower Tertiary remains essentially undeveloped.

INNOVATIVE SOLUTION

Fig. 2. The FrPS’s core technology is a moveable wellbay installed in place of a standard subsea MODU. Outboard well positioned under rotary (a).
Fig. 2. The FrPS’s core technology is a moveable wellbay installed in place of a standard subsea MODU. Outboard well positioned under rotary (a).

In response to the hurdles that have stalled development of the Lower Tertiary, Frontier Deepwater Appraisal Solutions (FDAS) has conceived a simpler, adaptive and standardized system that allows operators to capture critical dynamic reservoir data with a phased development strategy. The basic concept involves converting a 6th- or 7th-generation MODU capable of drilling Paleogene wells from top to bottom. Operators will have direct access to critical well systems equipment because the converted unit will maintain full drilling capabilities.

Wellbay centered and locked for hurricane (b).
Wellbay centered and locked for hurricane (b).

The conversion includes removing the marine drilling riser, subsea BOP and DP system, which frees up ample space and weight to install a production module and moveable wellbay, Fig. 2. As a result, the modified system incorporates a full 2.5 MM lb drilling, completion, intervention, workover and sidetrack rig on a 65,000 bopd production platform.

The deepwater Frontier Production System (FrPS) reduces risk and costs by building on the precepts that have worked successfully for onshore shale fields, including:

  • Use reliable completions and technology
  • Provide inexpensive drilling, completion, long-term maintenance and intervention
  • Use the pad concept to drill and develop a “cube,”
    which in this case is more reservoir acreage than
    contained in one OCS block.

The patented, movable wellbay technology provides billions of dollars in economic advantages over more expensive, less reliable 20,000-psi subsea developments. An FrPS incorporating the movable wellbay can be delivered and installed in about half the time and cost of a purpose-built subsea “hub” system and, because it is a phased approach, operators can confidently and profitably sanction initial field developments with fewer up front appraisal wells (2 or 3 instead of the 5 or 6 that has been standard so far). Depending on reservoir performance, the operator can subsequently add future phases faster (or condemn the asset) at less cost than is possible with the subsea-hub approach.

Fig. 3. The FrPS reduces the time from discovery to first oil by eliminating wasteful appraisal wells and reducing time for facilities build, install, commissioning.
Fig. 3. The FrPS reduces the time from discovery to first oil by eliminating wasteful appraisal wells and reducing time for facilities build, install, commissioning.

Further, the FrPS is a dry tree solution; dry tree completions have historically delivered much higher reserve recovery compared to wet trees. For a complex 400-MMbbl resource, this advantage may mean as much as 100 MMbbl of additional lifetime production, which would add $5 billion in revenue, compared with a subsea system. Due to the speed at which first and peak production can be achieved by reducing the number of appraisal wells to sanction a five-well development, this revenue “bonus” comes at the front end of the project, doubling the value of early adoption, Fig. 3. The FrPS provides these benefits using:

  • A converted 6th-generation semisubmersible
  • A 65,000-bopd production module
  • A moveable wellbay supporting five dry tree wells
  • A permanent taut-leg mooring system
  • Oil and gas export risers with pipeline tie-ins to regional infrastructure.

Shifting the appraisal paradigm.Let’s review several of the large industry discoveries. BP discovered Kaskida in 2006, and yet 13 years later, despite the 3 Bbbl thought to be in-place, it still has not been developed. BP has drilled a total of nine wellbores costing several billion dollars and still cannot come up with a 20,000-psi subsea production development plan that is economic. Anadarko discovered Shenandoah in 2009. After 10 years and the drilling of 14 appraisal boreholes, Anadarko was unable to come up with a workable 20,000-psi subsea development plan. Again, several billion dollars were expended to acquire well logs and cores. However, no dynamic reservoir performance or completion information was obtained, which are critical to answering key commercial questions needed to sanction the development.

Fig. 4. Cost comparison of a Phase 1 development of five wells to a full-field sanction requiring 10 producing wells, or more to justify a new facility. (Does not include appraisal well costs).
Fig. 4. Cost comparison of a Phase 1 development of five wells to a full-field sanction requiring 10 producing wells, or more to justify a new facility. (Does not include appraisal well costs).

The FrPS provides operators with the means to move forward more quickly with fewer appraisal wells while obtaining the dynamic reservoir information profitably at oil prices of less than $50/bbl. The total installed cost of the FrPS is less than half that of a new subsea hub development, and first oil is accelerated by several years while providing the dynamic reservoir information required to fully optimize field development, Fig. 4. A Phase 2 development can include subsea tiebacks or even another FrPS to maximize resource recovery.

The cost comparison shows that the savings are not coming from platform costs; those are similar. The increased efficiencies come from the significant reduction in drilling and completion costs by using a platform rig versus a dedicated HPHT MODU. The rig is purchased on the FrPS, and the operating dayrate is the drilling contractor services and crew along with the loaded dayrate services associated with dry tree operations. Historically, these dayrates are less than half of a MODU operating on a subsea field (reference Mad Dog, Holstein and Mars).

CASE STUDY

Fig. 5. Application of FrPS system showing economics at $45/bbl on one block containing five wells and three sidetracks.
Fig. 5. Application of FrPS system showing economics at $45/bbl on one block containing five wells and three sidetracks.

The FrPS system can help operators save billions of dollars on appraisal wells and effectively de-risk their deepwater projects. The FrPS system provides operators key information required to get the most recovery from the resource at the lowest possible cost and risk. To highlight the potential benefit of the FrPS system, a hypothetical case study is presented, using an initial well production rate of 15,000 bopd, based on existing BSEE production data from Lower Tertiary production. Figure 5 shows the resulting economics of a five-well FrPS at a $45/bbl flat oil price, including royalty and operating cost. The system is robust—even at $45/bbl—providing 20% IRR and $1.2 billion-dollar NPV at a 10% discount rate.

Fig. 6. Poor financial performance of a Lower Tertiary field developed with a subsea hub concept.
Fig. 6. Poor financial performance of a Lower Tertiary field developed with a subsea hub concept.

This compares favorably to several other fields developed with a subsea hub concept that have been plagued with poor bottom hole locations and complex subsea hardware reliability problems. These issues have resulted in expensive downtime and/or maintenance from DP MODU’s operating at more then $1 million per day. These fields were developed with existing 15,000-psi technology, and have been an operations challenge. Figure 6 shows an example of one of these fields using current production history from publicly available BSEE information at $55/bbl. With these poor economic results, the commercial viability of these projects are in serious doubt.

The FrPS is needed to change the game to win in the Lower Tertiary. With dynamic reservoir information obtained from this initial five-well development, operators may proceed with additional phases in possession of a higher degree of reservoir certainty. Frontier’s phased approach provides operators with significantly more value than the traditional subsea development scenario.

CONCLUSION

For decades, as operators moved to deeper water and more complex environments, the E&P industry has repeatedly turned to engineering innovation to meet evolving technological and economic challenges. To exploit the vast reserves of the Lower Tertiary, the industry must once again turn to engineering innovation rather than attempting to mutate a subsea supply chain solution built for other reservoir types in which drilling, completion and maintenance are not the cost drivers, as in the Lower Tertiary. The FrPS is an engineering innovation—a step change centered on the realization that, unlike times past, it is the cost of drilling and completion, as well as access to dynamic reservoir data, and not the production facility that must drive development decisions.

The FrPS is a solution for the Lower Tertiary because a phased approach reduces cost and risk as follows:

  • Reduces appraisal well requirements
  • Reduces spend by 50% compared to a subsea development
  • Delivered in 3 years or less
  • Eliminates the need for drillship contract
  • Earlier dynamic reservoir information
  • Increases completion access and reserve recovery with direct vertical access
  • Safer hydraulic controlled equipment
  • Permanently moored with fully rated dual barrier risers
  • Standardized develop scheme
  • Can be moved and reused over a wide range of water depths.

The moveable wellbay technology is also applicable to new construction. For example, TLPs and deep-draft floaters, such as spars, benefit, because the rig may be built lower into the platform, eliminating the heavy and expensive rig skidding systems on the top deck. In doing so, the drilling systems and utilities become simpler, and the overall platform size and complexity can be reduced.

About the Authors
Roy Shilling
Frontier Deepwater Appraisal Solutions LLC
Roy Shilling is president of Frontier Deepwater Appraisal Solutions, LLC with over 40 years of deepwater development experience at BP America, including assignments as the delivery manager for GOM HPHT floating systems, risers and topsides. He was a key leader on BP’s Project 20KTM and also worked on the Lower Tertiary project team. Mr. Shilling later worked extensively with Anadarko and Chevron on their 20K development efforts. He was an engineering or delivery manager on a number of BP’s deepwater projects including Horn Mountain, Holstein, Mad Dog, Thunderhorse and Atlantis. He has extensive drilling and completion experience and worked as a Senior Principal Drilling Engineer offshore on both jackups and floaters. During the BP Macondo incident, Mr. Shilling patented the first freestanding riser subsea containment system installed in 51 days and successfully operated with the Helix Producer I. In 2018, he received U.S. patents on the moveable wellbay, which can be installed on a converted or newbuild semisubmersible MODU to create a multi-well dry tree drilling and production system, targeted primarily as a Phase 1 development to de-risk and substantially reduce costs for Lower Tertiary discoveries. Frontier provides consulting services for deepwater projects worldwide. Mr. Shilling graduated with a BS degree in mechanical engineering from Vanderbilt University and earned an MS degree in ocean engineering from Texas A&M University.
Chuck White
Frontier Deepwater Appraisal Solutions LLC
Chuck White Frontier’s EVP and co-founder, is a naval architect (University of Michigan, 1975), who earned a master’s degree in mechanical engineering from University of Houston in 1983. He is a Fellow and past chairman of SNAME Texas. Mr. White worked for IOCs for 20+ years as a project manager and deepwater technology leader. Since 2000, he has worked primarily on technology development and deepwater and natural gas industry projects. He has led several large joint industry projects, as well as the API global task forces in writing the FPS and riser design RPs.  He also co-chaired creation of the first probabilistic riser design code. He holds multiple U.S. and international patents. 
Vamsee Achanta
Frontier Deepwater Appraisal Solutions LLC
Vamsee Achanta is Frontier's vice president of engineering and owner of AceEngineer. He is an upstream engineer with strong experience in the offshore sector. Mr. Achanta has 21 years of experience and holds a masters degree in mechanical engineering from Texas A&M (2003). His project experience spans facilities design, including SURF, moorings and floaters. Mr. Achanta specializes in data science O&G asset lifecycle automations from cradle to grave. 
Paul Hyatt
Frontier Deepwater Appraisal Solutions LLC
Paul Hyatt is Frontier’s vice president for drilling and completions and managing director of TD Solutions Pty Ltd. He is a wells specialist in all phases of well design and operations, from exploration to full-field development. His experience has stretched the globe for 43 years, including technical and project management roles in offshore, deep water, arctic operations, remote heli-rig exploration, HTHP completions, extended-reach design and installations, and decommissioning for various major operators and clients. Mr. Hyatt has a BS degree in petroleum engineering with honors from the University of Texas at Austin and is a life member of the Society of Petroleum Engineers. 
Howard Day
Frontier Deepwater Appraisal Solutions LLC
Howard Day
Related Articles FROM THE ARCHIVE
Connect with World Oil
Connect with World Oil, the upstream industry's most trusted source of forecast data, industry trends, and insights into operational and technological advances.